This week at ECI, we have completed the commissioning of three Solid Transport Units via Screw Conveyor. Each unit consists of a cradle-channel with a double screw system (one turning right and the other left), which, over nearly 12 meters in length, allows for uniform mixing and discharge throughout the entire path.
Next week, we will carry out the delivery and validation with the client. Immediately afterward, we will proceed with the commissioning of three additional units with a closed tubular conduit for the same installation. The final commissioning will take place in the coming months on Réunion Island (France).
Usamos cookies para asegurar que te damos la mejor experiencia en nuestra web. Si continúas usando este sitio, asumiremos que estás de acuerdo con ello. Política de privacidad
Puedes revocar tu consentimiento en cualquier momento usando el botón de revocación del consentimiento.
This week at ECI, we have completed the commissioning of three Solid Transport Units via Screw Conveyor. Each unit consists of a cradle-channel with a double screw system (one turning right and the other left), which, over nearly 12 meters in length, allows for uniform mixing and discharge throughout the entire path.
Next week, we will carry out the delivery and validation with the client. Immediately afterward, we will proceed with the commissioning of three additional units with a closed tubular conduit for the same installation. The final commissioning will take place in the coming months on Réunion Island (France).
📞 +34 93 864 83 65
✉️ eci@tallereseci.com