We celebrate the successful close of the first manufacturing phase of two tanks of impressive dimensions: Ø 3 metres x 7 metres, built entirely in AISI 316-L stainless steel with an astonishing capacity of 5,000 litres.
After completing rigorous tests, including leak-tightness, weld radiography and dimensional control, these tanks were moved to our adjoining facilities. Here, important processes will be carried out such as pickling and passivation, fitting the agitator, stairs and manhole, fixing the railings and the thermal lining.
Once all inspection points have been completed and verified, our efficient team will transport them using the trailers of our logistics partner to our client’s factory. Once positioned in their halls, we will proceed with the installation, piping and auxiliary equipment in the production area.
The much-anticipated second manufacturing phase is scheduled to start in early 2024. Our whole team has worked in a coordinated and effective way to meet the objective set by our client. Congratulations to everyone on the excellent work!